Construction Update: June 15, 2010

Phase II construction is in full gear. The sanitary sewer installation is complete, along with the water main, storm sewer and service line installation.

VS Engineering continues construction layout. IPL and Infra-Source have completed temporary power.

Road sub-grade prep has started and continues, however the frequent storms have interfered. Stone sub-base will start this week.