Redevelopment Construction Updates


Main Street is shifting into high gear! Construction has begun on Main Street and in The Speed Zone. The dirt is moving on Phase One and the project is on schedule to be completed by May 2010, just in time for the month-long celebration of the Indianapolis 500.


Check back for periodic construction updates and photos showing our progress below.


Main Street Construction Timeline:


Phase I: Closed from 11th Street to 13th Street until May 2010
Phase II: Closed from 10th Street to 11th Street from June 2010 to July 2010
Phase III: Closed from 13th Street to the middle of the 1400 block from August 2010 to October 2010
Phase IV: Closed from the middle of the 1400 block to 16th Street from October 2010 to May 2011


July 27, 2010

Phase 3 of the Main Street project is anticipated to start Monday, August 9th.  Construction signage will be placed a few days prior to that start date.

We will continually work on parking availability throughout Phases 3 and 4 and will post updates as each new solution emerges.

Periodic construction updates will also continue throughout Phases […]


(more)

June 15, 2010

Phase II construction is in full gear. The sanitary sewer installation is complete, along with the water main, storm sewer and service line installation.
VS Engineering continues construction layout. IPL and Infra-Source have completed temporary power.
Road sub-grade prep has started and continues, however the frequent storms have interfered. Stone sub-base will start this week.   


(more)

May 2, 2010

Phase I of Main Street opens to traffic on Monday, May 3rd!
Phase I of the Main Street construction project will open to traffic on time and on budget. Visit Main Street to view the new bike paths, rain gardens, expanded sidewalks and more.
Access to side and rear parking for 1201 and […]


(more)

April 22, 2010

Phase I of Main St. construction is almost done!!!
We’re right on schedule for completion of Phase I on April 30th. Trees and plants are going in this week, as are light posts.
Next week you’ll see benches and trash receptacles lining the street. The final coat of asphalt will be applied at the end of this […]


(more)

March 9, 2010

Underground water, sewer and sanitary work is complete!
There are many other activities occuring on Main St.: 
American Utility Corp., a contractor for AT&T continutes to work on the relocation of new lines. Calumet has started rough road grading with will perform sub-grade treatment. MCI completed lowering of their line. IPL has begun installing conduit at 12th St. InfraSource, […]


(more)

February 12, 2010

As the Main Street construction project moves forward, residents and business owners will be able to see real progress. Road grading may start as early as next week, as pipe installation is completed. Construction of the curb on the west side of Main Street, which will eventually run from 10th Street […]


(more)

January 29, 2010

Main Street pavers are on display in the parking lot of Speedway Town Hall. The signs show designation for sidewalks, crosswalks and parking areas. Please take a few minutes to stop by so you can visualize the vast improvements to come!
Construction is progressing on schedule, but it is still predominantly subsurface.
AT&T […]


(more)

December 14, 2009

Workers will begin laying water pipes at 10th St. and head north on Main St. Sanitary sewer lines will also start being placed at 11th St. going north, then from 11th St. going south. AT&T will also begin their underground work. Miller Pipeline and Citizen’s Gas contractors are in the process […]


(more)